Construction Update:


The final paving operations at Midway Rd. and Montfort Dr. that were scheduled for last night (Mon. Aug. 3rd) was not able to be completed and has been scheduled for tonight, Tuesday Aug. 4th from 7 p.m. to 6 a.m. Wednesday.

Again, the closures and detours associated for each intersection are as follows:

MIDWAY RD.
• Midway Rd. bridge at intersection of 635
- Westbound frontage road will be forced to take the bypass over Midway to Marsh Ln.
- Eastbound frontage road traffic trying to access northbound Midway will take Welch Rd. to McEwen

MONTFORT
• Montfort bridge at intersection of 635
- Eastbound frontage road at Montfort will be directed to Noel, Harvest Hill and Preston Rd.
- Westbound frontage road traffic will be directed north on Preston to Alpha in order to access Montfort.